济南富强门业有限公司网站 在线留言 联系我们

服务咨询热线

151 6888 2846

热门关键词: 水晶折叠门 水晶卷帘门 抗风卷帘门

公司新闻

首页>>新闻资讯>>公司新闻保证卷帘门安装质量方式
联系我们
济南富强门业有限公司

联系人:林经理

电话:151 6888 2846

邮箱:527800164@qq.com

地址:济南市历下区化纤厂路8号3号楼101号

保证卷帘门安装质量方式

来源:http://www.jnzxmy.com 日期:2021-12-06 发布人:
卷帘门施工工艺程序
Construction process procedure of rolling shutter door
(1)手动卷帘门工艺程序:定位、放线一安装卷筒一安装手动机构一帘板与卷筒连接一安装导轨一试运转一安装防护罩。
(1) Process procedure of manual rolling shutter door: positioning and setting out - Installation of drum - Installation of manual mechanism - connection between curtain plate and drum - Installation of guide rail - Test Run - Installation of protective cover.
(2)电动卷帘门工艺程序:定位、放线_安装卷简一安装电机、减速器一安装电气控制系统一空载试车一帘板与卷筒连接_安装导轨一安装水幕喷啉系统一试运转一安装防护罩。
(2) Process procedure of electric rolling shutter door: positioning and setting out_ Installation of winding sheet - Installation of motor and reducer - Installation of electrical control system - no-load commissioning - connection between curtain plate and winding drum_ Install the guide rail, install the water curtain spraying system, test run and install the protective cover.
2.定位放线卷帘门安装方式有洞内安装、洞外安装、洞中安装三种。即卷帘门装在门洞内,帘片向内侧卷起;卷帘门装在门洞外,帘片向外卷起和卷帘门装在门洞中,帘片可向外侧或向内侧卷起。因此,定位放线时应根据设计要求弹出两导轨垂直线及卷简线并测量洞口标高。定位放线后,应检查实际预埋铁件的数量、位置与图纸核对,如不符合产品说明书的要求,应进行处理。
2. There are three installation modes of positioning and setting out roller shutter door: installation inside the tunnel, installation outside the tunnel and installation in the tunnel. That is, the rolling shutter door is installed in the door opening, and the curtain sheet is rolled up to the inside; The rolling shutter door is installed outside the door opening, the curtain sheet is rolled outward, and the rolling shutter door is installed in the door opening, and the curtain sheet can be rolled outward or inward. Therefore, during positioning and setting out, the vertical lines of the two guide rails and the winding center line shall be snapped according to the design requirements, and the elevation of the opening shall be measured. After positioning and setting out, the quantity and position of the actual embedded iron parts shall be checked and checked with the drawings. If they do not meet the requirements of the product manual, they shall be handled.
济南卷帘门
3.安装卷筒安装卷筒时,应使卷筒轴保持水平,并使卷筒与导轨之间距离两端保持一致,卷筒临时固定后进行检查,调整、校正合格后,与支架预埋铁件用电焊焊牢。卷筒安装后应转动灵活。
3. Install the drum. When installing the drum, keep the drum shaft horizontal and keep the distance between the drum and the guide rail consistent at both ends. After the drum is temporarily fixed, check it. After adjustment and correction are qualified, weld it firmly with the embedded iron parts of the support by electric welding. The drum shall rotate flexibly after installation.
4.帘板安装帘板事先装配好,再安装在卷筒上。门帘板有正反向,安装时要注意,不得装反。
4. Curtain plate installation the curtain plate shall be assembled in advance and then installed on the drum. The door curtain plate has positive and negative directions. Attention shall be paid during installation, and it shall not be installed reversely.
5.安装导轨按图纸规定位置线找直、吊正轨道,保证轨道槽口尺寸准确,上下一致,使导轨在同一垂直平面上,然后用连接件与墙体上的预埋铁件焊牢。
5. Install the guide rail, align and hang the rail according to the position line specified in the drawing, ensure that the size of the rail notch is accurate and consistent up and down, make the guide rail on the same vertical plane, and then weld it firmly with the embedded iron parts on the wall with connectors.
6.安装水幕喷淋系统防火卷帘门应安装水幕喷淋系统。水幕喷淋系统,应与总控制系统连接。安装后,应试验。
6. Install the water curtain spraying system. The fireproof rolling shutter door shall be installed with the water curtain spraying system. The water curtain spray system shall be connected with the main control system. After installation, the test shall be carried out.
7.试运转先手动试运行,再用电动机启闭数次,调整无卡住、阻滞及异常噪声等现象为合格。
7. The test run shall be conducted manually first, and then the motor shall be opened and closed for several times. It is qualified if there is no jamming, block and abnormal noise.
8.安装卷筒防护罩
8. Install the drum guard
以上的精彩内容就是小编今天为您提供的内容,更多的精彩内容来自: 济南卷帘门详情请点击我们的网站关注:http://www.jnzxmy.com
The above wonderful content is what Xiaobian provides for you today. More wonderful content comes from Jinan roller shutter door. For details, please click our website to pay attention to: http://www.jnzxmy.com

阅读/ Recommended reading

1.:快速卷帘门和普通卷帘门的配置不一样,因为快速卷帘门要实现卷帘门的自动升降和均匀快速,所以快速卷帘门需要的电机也是必须要高配置的高频电机才可以,而普通卷帘门因为只要实现升降,速...

卷帘门污渍如何清洗? 2024-04-09
电动卷帘门的调节方法 2024-04-07
如何选择适合家庭使用的快速卷帘? 2024-03-29
济南卷帘门的作用与特点 2024-03-22
快速卷帘门可以满足高性能物流的使用 2024-02-10
卷帘门的常见故障和维修方法 2024-01-25
卷帘门遥控器怎么配对 2024-01-18
车库电动卷帘门的选择要注意哪几点? 2024-01-13